A joint build between two infrastructure operators has brought metro fibre to twelve secondary cities, several months ahead of the original schedule. The work replaces shared microwave backhaul that had been carrying peak-hour traffic well beyond its design capacity.
Engineers involved in the project said the faster pace came mostly from permitting reform at the municipal level rather than any change in construction method. Right-of-way approvals that once took a quarter are now clearing in weeks in several districts.
Effect on retail pricing
Retail broadband prices in the affected cities have not moved yet, and analysts caution that backhaul is only one input. Last-mile economics, device costs and electricity tariffs continue to shape what subscribers actually pay.
The next phase targets eight additional cities, subject to financing that has not yet closed.